Risk Management System and Project Staff Education Program for Overseas Construction Project Using the Expert System
http://hdl.handle.net/10173/1612
http://hdl.handle.net/10173/161285ab268c-93dc-4812-b86e-94bf9ee1f0a0
名前 / ファイル | ライセンス | アクション |
---|---|---|
SMS07-135.pdf (128.2 kB)
|
|
Item type | 会議発表論文 / Conference Paper(1) | |||||
---|---|---|---|---|---|---|
公開日 | 2018-02-06 | |||||
タイトル | ||||||
タイトル | Risk Management System and Project Staff Education Program for Overseas Construction Project Using the Expert System | |||||
言語 | ||||||
言語 | eng | |||||
資源タイプ | ||||||
資源タイプ識別子 | http://purl.org/coar/resource_type/c_5794 | |||||
資源タイプ | conference paper | |||||
著者 |
Hirota, Yoichi
× Hirota, Yoichi |
|||||
抄録 | ||||||
内容記述タイプ | Abstract | |||||
内容記述 | The turnover of the Japanese contractors and the consulting firms has kept the same level since 1983, in spite of the fact that the size of domestic market is shrinking. This is why they do not have a proper management system, especially risk management system for the overseas construction projects. This study aims at building risk management system and developing education program that can be applied to reinforcing the ability, based on the author’s experience. Risk is defined as “uncertain factors which will occur as the project is progressed”. And risk management is defined as “Project Risk Management is to convert the uncertain factors occurring as the project is executed to definite factors.” Process of risk management is to identify uncertain factors, qualify them, quantify them and respond to them. The author proposed a list to identify the uncertain factors in the initial stage of a construction project with his experience. Size of risk is expressed in the following formula; RL= PB x IP PB: Probability of occurrence. IP: Size of impact to the project. Management Ability Level (ML) of a member of the project team is evaluated in the following formula; ML= KLx √<PE + CE> KL: Knowledge of the project. PE: Experience of Projects. CE: Experience of International Contract such as FIDIC. Risk Response Ability (RA) of a project member is evaluated as RA= ML/RL. RA of the project team shall lead to a proper selection of the ways to respond to a risk. To manage the risks properly, the Project Manager and the staff are required to have minimum knowledge of the other disciplines than the civil engineering. To fill various roles required for the Project Manager, the ability of management should be gained through experience and education. The author proposes the education program to meet such requirement. | |||||
書誌情報 |
Society for Social Management Systems Internet Journal 巻 3, 号 1, 発行日 2007-03 |
|||||
ISSN | ||||||
収録物識別子タイプ | ISSN | |||||
収録物識別子 | 2432-552X | |||||
著者版フラグ | ||||||
出版タイプ | VoR | |||||
出版タイプResource | http://purl.org/coar/version/c_970fb48d4fbd8a85 | |||||
出版者 | ||||||
出版者 | Society for Social Management Systems |