Applicability of Multi-Party Risk and Uncertainty Management Process : Benefits from Its Application on an Infrastructure Project
http://hdl.handle.net/10173/1778
http://hdl.handle.net/10173/177845addde2-9f4f-42b8-98fb-d39ddfa82d1d
名前 / ファイル | ライセンス | アクション |
---|---|---|
SMS09-120.pdf (307.2 kB)
|
|
Item type | 会議発表論文 / Conference Paper(1) | |||||
---|---|---|---|---|---|---|
公開日 | 2018-02-06 | |||||
タイトル | ||||||
タイトル | Applicability of Multi-Party Risk and Uncertainty Management Process : Benefits from Its Application on an Infrastructure Project | |||||
言語 | ||||||
言語 | eng | |||||
キーワード | ||||||
主題Scheme | Other | |||||
主題 | risk and uncertainty | |||||
キーワード | ||||||
主題Scheme | Other | |||||
主題 | risk management process | |||||
キーワード | ||||||
主題Scheme | Other | |||||
主題 | application of risk management process in infrastructure project | |||||
資源タイプ | ||||||
資源タイプ識別子 | http://purl.org/coar/resource_type/c_5794 | |||||
資源タイプ | conference paper | |||||
著者 |
Pipattanapiwong, Jirapong
× Pipattanapiwong, Jirapong× Watanabe, Tsunemi |
|||||
抄録 | ||||||
内容記述タイプ | Abstract | |||||
内容記述 | This paper demonstrates application of the multi-party risk and uncertainty management process (MRUMP) to a real infrastructure project located in a Southeast Asian country as a case study. There are two objectives for its application. The first objective is to discuss applicability of the MRUMP for further refinement and improvement. The second objective is to reveal lessons learnt resulting from outputs of the MRUMP as benefits for both practitioners currently working on site and prospective practitioners of future projects. The MRUMP is designed for proactively solving problem through problem awareness, problem identification and problem solving. From the application, it could illustrate the MRUMP’s benefits at least in the following aspects, i.e., 1) facilitating problem solving by integration of multiple parties’ views, 2) increasing attention on uncertainty, 3) enhancing assessment by valuation of probability and impact and 4) realizing efficient management measures of uncertainty. Moreover, the MRUMP can be used as a post-evaluation study to draw lessons learnt for similar projects in future. It is further expected that the MRUMP is applicable for contract evaluation, assistance in policy making, planning, and problem avoidance at early stage of project and problem solving at later stage of project. | |||||
書誌情報 |
Society for Social Management Systems Internet Journal 巻 5, 号 1, 発行日 2009-03 |
|||||
ISSN | ||||||
収録物識別子タイプ | ISSN | |||||
収録物識別子 | 2432-552X | |||||
著者版フラグ | ||||||
出版タイプ | VoR | |||||
出版タイプResource | http://purl.org/coar/version/c_970fb48d4fbd8a85 | |||||
出版者 | ||||||
出版者 | Society for Social Management Systems |