{"_buckets": {"deposit": "b1111205-a890-4786-b8d8-39e41cce56af"}, "_deposit": {"created_by": 2, "id": "979", "owners": [2], "pid": {"revision_id": 0, "type": "depid", "value": "979"}, "status": "published"}, "_oai": {"id": "oai:kutarr.kochi-tech.ac.jp:00000979", "sets": ["21"]}, "author_link": ["2612", "2613"], "item_5_biblio_info_7": {"attribute_name": "書誌情報", "attribute_value_mlt": [{"bibliographicIssueDates": {"bibliographicIssueDate": "2009-03", "bibliographicIssueDateType": "Issued"}, "bibliographicIssueNumber": "1", "bibliographicVolumeNumber": "5", "bibliographic_titles": [{"bibliographic_title": "Society for Social Management Systems Internet Journal"}]}]}, "item_5_description_4": {"attribute_name": "抄録", "attribute_value_mlt": [{"subitem_description": "This paper is about how a consortium of five Japanese companies (COJAAL: Consortium Japonais Pour L’Autoroute Algerienne) is undertaking to build a 399 km, six-lane, limited-access highway across northern Algeria. The paper starts with the bidding process, the evaluation method and the structure of contracts that govern the construction of the project on a design-build basis. Since the contractor is allowed to alter, and therefore is responsible for, highway routing to a certain extent, the paper describes how this discretionary power was exercised to determine the final location of the highway. The paper then goes on to outline organizational setup, physical and design parameters, procurement and logistics, and construction execution plans. As of February 2009, the contractor is about 29 months into the project, whose duration was originally set at 40 months. The paper highlights events and/or issues that have had time impacts since its commencement in September 2006. Some sections of the project have faced major landslides. Other sections are being impacted by a shortfall of critical materials such as crushed gravels for pavement. The contractor also experienced complications from having to build a project to the French standard when natural conditions in Algeria do not necessarily lend themselves to the French standard. Sourcing and mobilizing labor from out-of-the-country markets in sufficient numbers and having them work efficiently on a stretch of construction sites extending over hundreds of kilometers have added to the task of coordination and control. As such, the paper represents an interim report on, and a case study of, managerial and technical challenges that an overseas project of this magnitude and scope can present to the contractor, as well as approaches that can be taken to meet such challenges.", "subitem_description_type": "Abstract"}]}, "item_5_publisher_36": {"attribute_name": "出版者", "attribute_value_mlt": [{"subitem_publisher": "Society for Social Management Systems"}]}, "item_5_source_id_11": {"attribute_name": "ISSN", "attribute_value_mlt": [{"subitem_source_identifier": "2432-552X", "subitem_source_identifier_type": "ISSN"}]}, "item_5_version_type_19": {"attribute_name": "著者版フラグ", "attribute_value_mlt": [{"subitem_version_resource": "http://purl.org/coar/version/c_970fb48d4fbd8a85", "subitem_version_type": "VoR"}]}, "item_creator": {"attribute_name": "著者", "attribute_type": "creator", "attribute_value_mlt": [{"creatorNames": [{"creatorName": "Iwabuchi, Akira"}], "nameIdentifiers": [{"nameIdentifier": "2612", "nameIdentifierScheme": "WEKO"}]}, {"creatorNames": [{"creatorName": "Shimizu, Tsuneyoshi"}], "nameIdentifiers": [{"nameIdentifier": "2613", "nameIdentifierScheme": "WEKO"}]}]}, "item_files": {"attribute_name": "ファイル情報", "attribute_type": "file", "attribute_value_mlt": [{"accessrole": "open_date", "date": [{"dateType": "Available", "dateValue": "2019-02-13"}], "displaytype": "detail", "download_preview_message": "", "file_order": 0, "filename": "SMS09-155.pdf", "filesize": [{"value": "263.4 kB"}], "format": "application/pdf", "future_date_message": "", "is_thumbnail": false, "licensetype": "license_free", "mimetype": "application/pdf", "size": 263400.0, "url": {"label": "SMS09-155.pdf", "url": "https://kutarr.kochi-tech.ac.jp/record/979/files/SMS09-155.pdf"}, "version_id": "3a0ff5d4-216a-4fa8-9b12-70aa078ed7f5"}]}, "item_keyword": {"attribute_name": "キーワード", "attribute_value_mlt": [{"subitem_subject": "highway construction", "subitem_subject_scheme": "Other"}, {"subitem_subject": "design-build management", "subitem_subject_scheme": "Other"}, {"subitem_subject": "construction standards", "subitem_subject_scheme": "Other"}]}, "item_language": {"attribute_name": "言語", "attribute_value_mlt": [{"subitem_language": "eng"}]}, "item_resource_type": {"attribute_name": "資源タイプ", "attribute_value_mlt": [{"resourcetype": "conference paper", "resourceuri": "http://purl.org/coar/resource_type/c_5794"}]}, "item_title": "The Algeria East-West Highway : An Interim Report", "item_titles": {"attribute_name": "タイトル", "attribute_value_mlt": [{"subitem_title": "The Algeria East-West Highway : An Interim Report"}]}, "item_type_id": "5", "owner": "2", "path": ["21"], "permalink_uri": "http://hdl.handle.net/10173/1770", "pubdate": {"attribute_name": "公開日", "attribute_value": "2018-02-06"}, "publish_date": "2018-02-06", "publish_status": "0", "recid": "979", "relation": {}, "relation_version_is_last": true, "title": ["The Algeria East-West Highway : An Interim Report"], "weko_shared_id": -1}
  1. SSMSパブリケーション
  2. Vol.05

The Algeria East-West Highway : An Interim Report

http://hdl.handle.net/10173/1770
http://hdl.handle.net/10173/1770
42682ee3-3d59-4722-9bee-85ad4793a96f
名前 / ファイル ライセンス アクション
SMS09-155.pdf SMS09-155.pdf (263.4 kB)
Item type 会議発表論文 / Conference Paper(1)
公開日 2018-02-06
タイトル
タイトル The Algeria East-West Highway : An Interim Report
言語
言語 eng
キーワード
主題Scheme Other
主題 highway construction
キーワード
主題Scheme Other
主題 design-build management
キーワード
主題Scheme Other
主題 construction standards
資源タイプ
資源タイプ識別子 http://purl.org/coar/resource_type/c_5794
資源タイプ conference paper
著者 Iwabuchi, Akira

× Iwabuchi, Akira

WEKO 2612

Iwabuchi, Akira

Search repository
Shimizu, Tsuneyoshi

× Shimizu, Tsuneyoshi

WEKO 2613

Shimizu, Tsuneyoshi

Search repository
抄録
内容記述タイプ Abstract
内容記述 This paper is about how a consortium of five Japanese companies (COJAAL: Consortium Japonais Pour L’Autoroute Algerienne) is undertaking to build a 399 km, six-lane, limited-access highway across northern Algeria. The paper starts with the bidding process, the evaluation method and the structure of contracts that govern the construction of the project on a design-build basis. Since the contractor is allowed to alter, and therefore is responsible for, highway routing to a certain extent, the paper describes how this discretionary power was exercised to determine the final location of the highway. The paper then goes on to outline organizational setup, physical and design parameters, procurement and logistics, and construction execution plans. As of February 2009, the contractor is about 29 months into the project, whose duration was originally set at 40 months. The paper highlights events and/or issues that have had time impacts since its commencement in September 2006. Some sections of the project have faced major landslides. Other sections are being impacted by a shortfall of critical materials such as crushed gravels for pavement. The contractor also experienced complications from having to build a project to the French standard when natural conditions in Algeria do not necessarily lend themselves to the French standard. Sourcing and mobilizing labor from out-of-the-country markets in sufficient numbers and having them work efficiently on a stretch of construction sites extending over hundreds of kilometers have added to the task of coordination and control. As such, the paper represents an interim report on, and a case study of, managerial and technical challenges that an overseas project of this magnitude and scope can present to the contractor, as well as approaches that can be taken to meet such challenges.
書誌情報 Society for Social Management Systems Internet Journal

巻 5, 号 1, 発行日 2009-03
ISSN
収録物識別子タイプ ISSN
収録物識別子 2432-552X
著者版フラグ
出版タイプ VoR
出版タイプResource http://purl.org/coar/version/c_970fb48d4fbd8a85
出版者
出版者 Society for Social Management Systems
戻る
0
views
See details
Views

Versions

Ver.1 2023-05-15 13:20:04.142403
Show All versions

Share

Mendeley Twitter Facebook Print Addthis

Cite as

エクスポート

OAI-PMH
  • OAI-PMH JPCOAR
  • OAI-PMH DublinCore
  • OAI-PMH DDI
Other Formats
  • JSON
  • BIBTEX

Confirm


Powered by WEKO3


Powered by WEKO3