Reconstruction of Provincial Highway No.13 Hou-Feng Bridge Damaged by Typhoon Sinlaku

http://hdl.handle.net/10173/1040
http://hdl.handle.net/10173/1040
8d7af125-09a3-4480-b5ed-a669028ff791
名前 / ファイル ライセンス アクション
sms12-1298.pdf sms12-1298.pdf (1.6 MB)
Item type 会議発表論文 / Conference Paper(1)
公開日 2013-10-25
タイトル
タイトル Reconstruction of Provincial Highway No.13 Hou-Feng Bridge Damaged by Typhoon Sinlaku
言語
言語 eng
キーワード
主題Scheme Other
主題 Typhoon Sinlaku
キーワード
主題Scheme Other
主題 reconstruction
キーワード
主題Scheme Other
主題 temporary access road
キーワード
主題Scheme Other
主題 temporary access bridge
資源タイプ
資源タイプ識別子 http://purl.org/coar/resource_type/c_5794
資源タイプ conference paper
著者 Huang, Ping-Hsun

× Huang, Ping-Hsun

Huang, Ping-Hsun

Search repository
Chen, Hsin-Chih

× Chen, Hsin-Chih

Chen, Hsin-Chih

Search repository
Liaw, Yeong-Jong

× Liaw, Yeong-Jong

Liaw, Yeong-Jong

Search repository
Chang, Tyng-Lo

× Chang, Tyng-Lo

Chang, Tyng-Lo

Search repository
抄録
内容記述タイプ Abstract
内容記述 Typhoon Sinlaku brought a heavy rainfall on September 14, 2008. The P2 pie of Houfeng bridge was washed away by rushed Tachia Hsi river water. It caused part of the bridge deck collapsed and the traffic from Houli and Fengyuan was interrupted at once. In order to resume the traffic as soon as possible, Directorate General of Highways, MOTC planed a rehabilitation strategy which was including short-term rehabilitation scheme adopting temporary access road, intermediate rehabilitation scheme using temporary access bridge and long-term rehabilitation scheme building permanent bridge. The main purpose of the plan was to reduce the social cost and improve the traffic safety in typhoon season. The bridge was under reconstruction when the disaster occurred. Because of the disaster, the original construction method using half-half construction in three stages keeping the traffic in service was intergraded to one construction stage since the bridge was collapsed. The construction time was shortened from 973 days to 540 days. The new Houfeng bridge was opened to traffic part by part. After 9 months, a 440 meters long 4 lines in two ways partial new bridge was completed for service. After 20 months, the whole bridge with 440 meters 10 lines in two ways was finished to fulfill the long-term rehabilitation goal.
書誌情報 Society for Social Management Systems Internet Journal

巻 8, 発行日 2012-05
著者版フラグ
出版タイプ VoR
出版タイプResource http://purl.org/coar/version/c_970fb48d4fbd8a85
出版者
出版者 Society for Social Management Systems
戻る
0
views
See details
Views

Versions

Ver.1 2023-05-15 13:14:27.303240
Show All versions

Share

Mendeley Twitter Facebook Print Addthis

Cite as

エクスポート

OAI-PMH
  • OAI-PMH JPCOAR 2.0
  • OAI-PMH JPCOAR 1.0
  • OAI-PMH DublinCore
  • OAI-PMH DDI
Other Formats
  • JSON
  • BIBTEX

Confirm


Powered by WEKO3


Powered by WEKO3